Frank J. Guarini Justice Complex

Frank J. Guarini Justice Complex
Interactive map of the Frank J. Guarini Justice Complex area
General information
StatusCompleted
LocationJersey City, NJ, United States, 24 Central Ave., Jersey City, NJ
Coordinates40°43′59″N 74°03′25″W / 40.733°N 74.057°W / 40.733; -74.057
Named forFrank J. Guarini
Groundbreaking24 January 2021[1]
Topped-out9 September 2022[2]
Estimated completion
October 2024[3]
OpenedJune 6, 2026[4]
Cost345 million USD[3]
OwnerHudson County Improvement Authority
Technical details
Size405,000 sqft
Design and construction
ArchitectRafael Viñoly
Architecture firm
Netta Architects[5]
Structural engineer
O'Donnell & Naccarato[5]
Main contractorTerminal Construction Corporation
Other information
Parking471-space garage
Website
hudsoncountycourthouse.com

The Frank J. Guarini Justice Complex is a judicial complex in Jersey City, New Jersey, that opened in 2026. The complex comprises a five-story building, a one-and-a-half-story building, and a six-story parking garage, that replaces the Hudson County Administration Building, which was built in 1957.[3][5] The complex is named after New Jersey Democratic politician Frank J. Guarini.

Design

The complex shares a single foundation and includes three buildings: a five-story offices and courthouses, a one-and-half story building for Surrogate court, and a six-story, 471-space parking garage.[3][6] The parking garage has shorter floors than the main building, allowing the five-story courthouse to overhang the six-story garage. A three-story ramp connects the lobby with the main courthouse, providing access while avoiding the higher security lower levels.[5][6] The complex features a 75-seat cafeteria, a self-help law library, a children’s play area and staff training spaces.[4]

The eastern side of the complex, showing the parking garage and admin floors above

Security

The building has several structural safety features, including ballistic rated windows and protection from a total collapse due to an explosion.[6] The new complex also seeks to address security issues that the previous building had, including separate entrances for the public, staff, and inmates, as well as having areas with differing levels of security based on their function.[3]

See also

References

  1. ↑ ""Honorable Frank J. Guarini Justice Complex"". Hudson County Courthouse. Retrieved 16 October 2023.
  2. ↑ "Hudson County Justice Complex Construction Progress Continues with Steel Topping out and Removal of Temporary Supports". hudsoncountycourthouse.com. 19 October 2022. Retrieved 16 October 2023.
  3. 1 2 3 4 5 Maher, Jake (24 May 2022). "Massive new Hudson County courthouse, with modern design and better security, on track for 2024 finish". nj.com. Retrieved 16 October 2023.
  4. 1 2 "Hudson County Opens New $350 Million Justice Complex in Jersey City". Correctional News. June 15, 2026. Retrieved August 3, 2026.
  5. 1 2 3 4 Reid, Robert L. (6 April 2023). "Trusses help protect court complex from blast-induced progressive collapse". ASCE.org. ASCE. Retrieved 16 October 2023.
  6. 1 2 3 Loder, Stephanie (2 October 2023). "NJ Court Complex Renovated to Withstand Disasters". ENR New York. Retrieved 16 October 2023.