Union Hospital station

Union Hospital

協和醫院
Entrance and exit signs of Union Hospital station
General information
LocationEstrada do Istmo, Cotai, Macau
LineTaipaSeac Pai Van
Platforms2 side platforms, 2 island platforms
Construction
Structure type
Elevated
Other information
Station code ST18A 
History
OpenedTaipa line: 1 September 2024 (2024-09)
Seac Pai Van line: 1 November 2024 (2024-11)
Former namesIsland Hospital
Services
Preceding station Logo of Macau Light Rapid Transit Macau Light Rapid Transit Following station
Lotus
towards Barra
Taipa line East Asian Games
Terminus Seac Pai Van line Seac Pai Van
Terminus
Location

Union Hospital station (Chinese: 協和醫院站, Portuguese: Estação Hospital Union) is the interchange station for the Taipa Line and the Seac Pai Van line of the Macau LRT, and also the terminal station for the Seac Pai Van line. It is located between the Rotunda Flor de Lótus in Cotai and Estrada do Istmo, connecting to the Macau Union Hospital. This station is an elevated station, with pathways for transferring between the Taipa Line and the Seac Pai Van line.[1]

Station layout

Station lobby

The station is equipped with a customer service center, self-service ticket vending machines, entrance gates, ticketing information, street maps, exit instructions, etc., and is located on the Seac Pai Van line and shared with the Taipa line.[2]

Platforms and transfer

Union Hospital Station has four platforms, all of which are equipped with platform gates. The Taipa Line platform is a side platform, while the platform of the Seac Pai Van line is an island platform, located in the middle of the Cotai Connecting Highway, south of the Taipa Line station. Platform 3 is a platform used by both lines, while platform 4 is a backup platform for special occasions.[3][4]

The original plan and design of this station was to serve as one of the independent stations of the Seac Pai Van line, and the original plan and design of Lianhua Station was to become an interchange station for the "three-line intersection" between the Taipa Line, the Hengqin Line and the Seac Pai Van line.[5] In 2020, the revised plan canceled the original design and instead built this station near Lianhua Station on the Taipa Line, so that the Seac Pai Van line would terminate at this station and intersect with the Taipa Line. This results in a long distance between transfer channels.[6][7]

Usage

The Taipa Line platform and station lobby of this station opened on September 1, 2024.[2]

After the opening of the Seac Pai Van line, the platform for it on the south side of the station was also opened at the same time, as the first interchange station of the Macau Light Rail Link to be opened, but due to the long walking distance of the interchange passage and the need to get on and off the platform between the Taipa Line and the Seac Pai Van line, it is relatively inconvenient for some elderly people or people with reduced mobility.[8]

History

Early ideas

On 10 January 2014, the Transport Infrastructure Office launched the "Call for Opinions on the Feasibility Study of the Seac Pai Van line of the Macao Light Rail System", which lasted for 45 days and ended on 23 February. Among them, there are three options for the construction of this station and to be set up as an intermediate station on the Shek Pai Wan Line. Among them, the main station of Options 1 and 2 is located on the west side of the outlying islands medical complex, while the main station of Option 3 is located opposite the main entrance of the outlying islands medical complex.[9][10]

On 23 August 2015, the Transport Infrastructure Office announced the "Call for Opinions on the Feasibility Study of the Seac Pai Van line of the Macao Light Rail System" and recommended Option 1.[11]

Modified design

In 2019, the Taipa Line platform of this station has been reserved for connecting to the Seac Pai Van line.

On July 23, 2020, the station and the Seac Pai Van line conducted public bidding for the project.[1] The Construction and Development Office will conduct public tendering for the "C390B Light Rail Seac Pai Van line Main Construction Project", with a total construction period of 960 working days. For the first time, the tender announcement clearly abandoned the earlier recommended option 1, cancelled the original transfer plan of Lianhua Port Station, and replaced it with an additional interchange station between Lianhua Port Station and East Asian Games Station on the Taipa Line, thus reducing the number of stations on the route to two, and at the same time building a footbridge at this station to connect to the medical complex on the outlying islands.[12]

On 20 May 2021, after reviewing the tenders, the Construction and Development Office considered that the bidding amount and construction period of the bidders were significantly low, and there was a possibility of serious overspending, and the Construction Office had to revise the plans. Therefore, the Macau Government announced the withdrawal of the C390B tender and re-tendering at a later date.[13]。

On June 2, 2021, the "Main Construction Project of the Light Rail Seac Pai Van line" restarted the bidding process.[14]。

On June 29, 2021, the main project of the Light Rail Seac Pai Van line was opened, according to the Construction Office, after the bid opening process, 10 bids were accepted, and 1 was conditionally accepted, but the documents must be submitted within the specified date. The cost of the project ranges from MOP908 million to MOP1.008 billion, and the construction period ranges from 638 working days to 760 working days.[15]。

Construction

On August 13, 2021, the main project of the Light Rail Seac Pai Van line was officially awarded, and the construction was undertaken by China Road and Bridge Engineering Co., Ltd. for nearly 930 million patacas, and the project date was 685 working days.[16]

In October 2021, the first phase of construction of the main construction project of the Shek Pai Wan Line began.[17]。

In December 2021, the construction of the main construction project of the Seac Pai Bay Line entered the second phase.[18]

From October 29 to November 17, 2022, the station began construction of the transfer bridge and placed temporary gantry brackets in the existing traffic lanes.[19]

From December 1 to 21, 2022, the station carried out the hoisting construction of the connecting bridge of the transfer station.[20]

In mid-February 2023, the Public Works Bureau stated that the construction project was expected to be completed in February 2024.[21]

Conduct station testing

On 8 January 2024, the Secretary for Transport and Public Works, Mr Lo Lap-man, said that station and train tests had been commenced on the Seac Pai Van line, making it clear that the line would not be operated by the MTR (Macau). The light rail company was expected to be responsible for the more content awarded.[22]。

On March 31, 2024, the main project of the Seac Pai Van line was basically completed, and the station was renamed "Union Hospital Station", and various systems and train operation tests were carried out. The train test will be carried out in three phases, the first stage will be within the Seac Pai Van line, the second stage will be extended to the interchange station (Lotus Roundland) via the Taipa Line, and the third stage will be the entire line.[23]

Opening

On September 1, 2024, the station was partially opened, allowing passengers on the Taipa Line to go to Union Medical College Hospital of Macau through this station, while the Seac Pai Van line platform has not yet been activated.[24][25]。

On November 1, 2024, the Seac Pai Van line was officially opened to traffic, with the first train departing from Seac Pai Wan Station at 13:11 on the same day.[26] The station has been fully opened since then, making it the first interchange station in the Macau Light Rail Network.

References

  1. 1 2 "公告「C390B-輕軌石排灣線主體建造工程」公開招標" (in Traditional Chinese). Construction and Development Office. Archived from the original on 2020-07-29. Retrieved 2020-07-29.
  2. 1 2 "輕軌協和醫院站啟用" (in Chinese). Macao Daily News. 2024-09-02. Archived from the original on 2024-09-02. Retrieved 2024-09-02.
  3. ↑ "輕軌石排灣主體工程共收十份標書 工程料最快今年年底開展" [The main construction works for the Seac Pai Van line have received a total of ten bids; construction is expected to commence as early as the end of this year.]. Exmoo News (in Chinese). 8 September 2020. Retrieved 14 April 2026.
  4. ↑ "華僑報". www.vakiodaily.com (in Chinese). Retrieved 14 April 2026.
  5. ↑ "輕軌石排灣線方案一多支持 - 正報新聞". www.chengpou.com.mo (in Chinese). 2024-09-02. Retrieved 14 April 2026.
  6. ↑ "輕軌石排灣主體工程共收十份標書 工程料最快今年年底開展". 力報. 2020-09-08. Archived from the original on 2024-06-20. Retrieved 2024-09-02.
  7. ↑ "輕軌石排灣線主體工程完工公建局已臨時接收 設石排灣及離島醫院站". Macao Daily News. 2024-06-05. Archived from the original on 2024-06-04. Retrieved 2024-09-02.
  8. ↑ "居民冀輕軌石排灣線更方便". Macao Daily News. 2024-11-02.
  9. ↑ "輕軌石排灣線可行性研究 三方案延展綠色連繫" (in Traditional Chinese). Transport Infrastructure Office. Archived from the original on 2014-01-11. Retrieved 2014-08-03.
  10. ↑ "澳門輕軌系統石排灣線 可行性研究 意見徵集" (in Traditional Chinese). Transport Infrastructure Office. Archived from the original on 2014-01-10. Retrieved 2014-08-03.
  11. ↑ "輕軌石排灣線可行性研究意見徵集活動結果公佈" (in Traditional Chinese). Transport Infrastructure Office. Archived from the original on 2015-09-24. Retrieved 2015-08-23.
  12. ↑ "公告「C390B-輕軌石排灣線主體建造工程」公開招標" (in Traditional Chinese). Construction and Development Office. Archived from the original on 2020-07-29. Retrieved 2020-07-29.
  13. ↑ "公告 輕軌石排灣線工程短期將重新招標" (in Traditional Chinese). Construction and Development Office. Archived from the original on 2021-05-20. Retrieved 2021-05-20.
  14. ↑ "石排灣今日重新展開招標". Macao Daily News. Archived from the original on 2021-06-02. Retrieved 2021-06-02.
  15. ↑ "【二度開標】建設辦收11份標書競投石排灣線主體工程". 論盡媒體 AllAboutMacau Media. 2021-06-29. Archived from the original on 2021-06-29. Retrieved 2021-06-29.
  16. ↑ ""C390B – 輕軌石排灣線主體建造工程"的公開招標 判給結果" (PDF) (in Traditional Chinese). Transport Infrastructure Office. Archived from the original (PDF) on 2021-08-13. Retrieved 2021-08-13.
  17. ↑ "C390B-輕軌石排灣線主體建造工程第一階段施工臨時交通措施". Construction and Development Office. Government Information Bureau of the Macao Special Administrative Region. 30 September 2021. Archived from the original on 5 September 2022. Retrieved 11 March 2023.
  18. ↑ ""C390B-輕軌石排灣線主體建造工程" 第2階段施工臨時交通措施". Construction and Development Office. Government Information Bureau of the Macao Special Administrative Region. Archived from the original on 4 September 2022.
  19. ↑ "「C390B-輕軌石排灣主體建造工程」轉車站連接橋施工". 公共建設局(DSOP). Government Information Bureau of the Macao Special Administrative Region. 28 October 2022.
  20. ↑ "「C390B-輕軌石排灣主體建造工程」轉車站連接橋施工". Government Information Bureau of the Macao Special Administrative Region. 28 November 2022.
  21. ↑ "輕軌東線料二八年竣工". Macao Daily News. 2023-02-17. Archived from the original on 2023-02-17. Retrieved 2023-03-10.
  22. ↑ "輕軌東線料2029年開通使用 羅司:東線關閘站一定超支和超時". 2024-01-09. Archived from the original on 2024-01-10. Retrieved 2024-01-10.
  23. ↑ "輕軌石排灣線開展列車運行測試 測試列車已駛入橫琴線". Exmoo News. 2024-03-31. Archived from the original on 2024-03-31. Retrieved 2024-03-31.
  24. ↑ "輕軌協和醫院站九一可啟用". 正報. 2024-08-10. Archived from the original on 2024-09-19. Retrieved 2024-08-10.
  25. ↑ "輕軌協和醫院站9月1日率先使用 便利市民進出協和醫院". Government Information Bureau of the Macao Special Administrative Region. 2024-08-28. Archived from the original on 2024-08-28. Retrieved 2024-08-28.
  26. ↑ "輕軌石排灣線將於11月1日通車". Government Information Bureau of the Macao Special Administrative Region. 2024-10-29. Archived from the original on 2024-12-19. Retrieved 2024-10-29.