| Status | Operational |
| Construction began | 1976 |
| Opening date | 2009 |
| Owner | RusHydro |
| Dam and spillways | |
| Type of dam | Gravity dam |
| Impounds | Bureya River |
| Height | 140 m (460 ft) |
| Length | 736 m (2,415 ft) |
| Reservoir | |
| Total capacity | 20.94 GL (16,980 acre⋅ft)[1] |
| Surface area | 750 km2 (290 sq mi)[1] |
| Bureyskaya hydroelectric plant (Russian: Бурейская ГЭС) | |
| Coordinates | 50°16′12″N 130°18′49″E / 50.2701°N 130.3136°E |
| Operator | RusHydro |
| Commission date | 2010 |
| Type | Conventional |
| Turbines | 6 × 335 MW (449,000 hp) |
| Installed capacity | 2,010 MW (2.70×106 hp) |
The Bureya Dam (locally referred to as Bureyskaya, Russian: Бурейская ГЭС) is a hydroelectric dam on the Bureya River in the Russian Far East.
History
Bureya hydroelectric power station was built by Bureyagesstroy.[1] Construction started in 1976, but was halted until 1999. In 1999, RAO UES restarted the project. The dam was completed and the first unit was launched in 2003.[2] The construction of the whole complex was completed in 2009.[1]
The reservoir reached its specified level during the summer-autumn monsoon season of 2009. It was accompanied with first use of spillways during planned tests. Despite the fact that all primary construction works on power station was completed, it was officially commenced for exploitation by government commission in 2011. Therefore, officially, the complex is still under construction.
Description
The Bureya Dam is a gravity dam with height of 140 metres (460 ft) and crest length of 736 metres (2,415 ft).[3][4]
Owned by RusHydro, the Bureyskaya conventional hydroelectric plant has an installed capacity of 2,010 megawatts (2.70×106 hp). Power is generated by utilizing six turbines, each with a capacity of 335 MW (449,000 hp).[5]
Gallery
Bureya Reservoir
Spillways of Bureya HPP in work
See also
References
- 1 2 3 4 "Bureisk HPP". Bureyagesstroy. Retrieved January 22, 2011.
- ↑ "Dam Development in Russia". Amur-Heilong River Basin Information Center. Archived from the original on August 16, 2010. Retrieved January 22, 2011.
- ↑ "Общие сведения". Archived from the original on September 5, 2019. Retrieved May 23, 2016.
- ↑ "Bureya Dam". International Database and Gallery of Structures. Retrieved January 22, 2011.
- ↑ "Bureyskaya hydroelectric plant". Global Energy Monitor. March 17, 2026. Retrieved April 11, 2026.
External links
Media related to Bureya hydroelectric power plant at Wikimedia Commons